Urban Water Supply and Sanitation Project in Aden Governorate
- Client
Ministry of Water and Environment, Local Water and Sanitation and Corporation in Aden Governorate
- Location
Aden, Yemen
- Project Sector
Major Developments
Design and Development of Water Supply and Sanitation Project
Environmental audit, site visits, development of QHSE audit reports
The Aden Governorate is expanding enormously and safe water and distribution services are essential to meet the demands of the growing population. The project was divided into four tasks:
Task A | Development Programme
Preparation of a development plan to serve as a framework for the expansion up to 2025 for:
Water production, transmission and distribution facilities
Wastewater collection, treatment and effluent disposal or reuse
Investment requirements in five-year intervals
Key activities included
GIS mapping system
Population growth projections
Water demand scenarios
Leakage detection and asset condition
Hydraulic modelling using H2OMap and H2OMap Sewer
Design criteria for engineering designs
Wastewater discharge estimates
Effluent reuse
Extension and upgrading of wastewater collection, treatment and disposal
Financial analysis and investments
Assessment of environmental impact
Task B | Water Resource Assessment Study
Prepared in parallel to task A, this was for the rehabilitation of existing water sources and exploration of additional water resources. Key activities included:
Inventory of existing data, water resource studies
Defining geological and hydrological boundaries and aquifer systems
Geophysical surveys and well drilling activities
Preparation of groundwater and water quality models
Assessing present and future water production capacity
Investigation of desalination as a supplemental water source
The project included a formal technical training component on the water conveyance and distribution system, hydraulic modelling and GIS principles and software, as well as the concept of restructuring and zoning for proper management and loss reduction.
Task C | Feasibility Study
Provided detailed water and wastewater investments to preliminary engineering design up to the first phase of development in 2015.
Task D | Detailed Engineering Design
Detailed engineering designs and preparation of bidding documents for the water and wastewater components to meet the requirements of the first phase of development.